Early contractor involvement merged seamlessly with D&C on Great Northern Highway
|
Western Australia’s Great Northern Highway is the only sealed road connecting WA with the Northern Territory and is the main land transport route between Perth and the Kimberley. |
|
The construction camp
Subject to a harsh climate ranging from monsoonal wet seasons to desert-like dry months, 23km of the road in five sections over 170km between Halls Creek and Kunnunurra, needed upgrading to meet new standards.
Federal Government funding became available in 2007 under AusLink’s Accelerated Upgrade Package and sections were identified as a priority due to factors such as poor geometry and narrow seal width. Also, three bridges needed improved load capacity and better flood immunity.
Main Roads WA project director Mark Hazebroek, who was the project’s client representative, said it was not possible for works to be tendered under a traditional lump sum contract, because the project was not well defined.
“The funding was announced before early project development and approvals were in place. The boom was also in full swing, so we could not afford to tie up three designers and three constructors in a detailed bidding process at a time when both our and their resources were stretched. But we wanted a contract model that would deliver a fit for purpose solution, provide the certainty of a lump sum and which would have a low demand on Main Road’s resources.
Alliancing flexibility
“From experience we knew that alliancing style contracts provide the flexibility to deliver. We also knew how challenging it is contracting in the far north, where you need to rely on natural road building materials and must therefore tailor standards to suit the harsh conditions and available materials.
“For example, pavement material is sourced from gravel pits off the side of the road so we need to locate and test it to determine appropriate pavement material standards. Likewise, it is not a well defined process to agree flood serviceability of bridges. We undertake modelling and then used engineering judgement to work out design floods for bridges.
“You can’t use that approach with a conventional Design and Construct (D&C) project, because you have to be very prescriptive. Other challenges requiring a more collaborative approach included scarcity of water for construction purposes and significant logistics getting people and equipment to site.
“So we chose, a Main Roads WA first, an early contractor involvement (ECI) process for the project development phase and a design and construct (D&C) model for delivery, with relationship contracting elements and incentives throughout.
“We saw the benefits of collaborating with industry during the ECI phase to determine a scope of works within the $116m budget, as this would ensure funding could be allocated prudently and within the timeframe required.”
ECI tender process
Hazebroek said the ECI tender process requested competitive rates for plant, labour, staff and key construction activities as well as a percentage margin for corporate overhead and profit.
BGC Contracting, Laing O’Rourke Australia and AECOM Australia were selected from four tenderers to work with Main Roads during the ECI phase.
They were reimbursed actual costs during the 8 month ECI phase. Following an intense review period, the ECI phase concluded with Main Roads accepting the D&C fixed price and TS were awarded the second phase contract. The ECI phase set the scene for enhanced relationships through the D&C phase.
Establishing and maintaining relationships
TS agreed that co-location during the ECI phase was a fundamental requirement to maximise synergies of the diverse team and to support the ‘one-team’ culture being developed.
A special-purpose project office included a large open-plan work area, breakout areas for informal interactions, an Ideas Room which facilitated capture and development of innovations and various meeting rooms.
Hazebroek said collaborative principles were transitioned to the D&C phase by utilising a co-located site office and keeping the same governance and management teams as much as possible.
“We all knew each other when we started construction. There were no new people so relationships were very strong, even when inevitable D&C contractual issues arose.
“These discussions can get difficult at times but relationships remained strong at all levels. The same senior executives stayed on our project management board into the D&C phase, providing consistency in relationships. This team met monthly, unlike a traditional D&C where they would only meet every three months.
“We also kept the same consultants to maintain the focus on team health. This included allocating time for team building activities and asking for team feedback on relationship health through regular independent health check surveys. Our ECI Management Team transitioned into the Project Review Group and met monthly during the D&C phase; the same discipline managers were involved from the ECI phase.
“We also brought alliancing principles into the D&C contract by allocating a $1m performance pool, with the team setting performance targets for Key Result Areas (KRAs). The Project Management Board had to agree on how the team performed, whether targets were met and what were the benefits and lasting legacies for the environment and community.
“This was the first time Main Roads has included a performance bonus in a D&C contract and it worked well, driving the right behaviours. We were willing to allocate an incentive for these key outcomes and performance became a big topic of discussion. It kept the managers involved and focused on delivering outstanding outcomes.”
Achievements, challenges
The primary objective of the ECI phase was to fast-track scope development, statutory approvals and pricing of this remote infrastructure project. Tasks included detailed project planning, preliminary investigations and design, development of management plans, and preconstruction works where possible.
Hazebroek said early works were brought forward into the ECI phase from the D&C phase, which increased the ECI budget from $3.5m to $12m but provided overall budget savings including time gains.
“We built the camp as part of the ECI early works, even though it would normally be part of the D&C contract, to keep the project moving. We also constructed a side-track and identified and stock-piled gravels so we could have a quick start-up. You don’t have this flexibility under a traditional D&C contract,” he said.
“Another example of the benefits of a more flexible approach was the inclusion of an on-site designer during the construction phase to avoid delays with resolving design issues from a remote site. This would normally be left out of a lump sum price in an effort to save cost. Having a designer on site proved effective during construction to manage adjustments quickly, particular in relation to foundations, drainage, culvert locations and levels – basically wherever we interfaced with the natural environment.”
Budget certainty
Team Savannah produced an early indicative price to provide a benchmark for future changes and highlight high cost areas where innovation could generate the greatest savings.
Hazebroek said this also provided early warning that the available budget (which was not known to the team) was insufficient for the intended project scope.
“This led to the scope being tailored to suit the available budget, saving considerable time and resources and avoided potential delays of re-scoping and re-pricing in the event that the final priced scope exceeded the budget. The collaborative process also enabled a very distinct allocation of risk and it was clear which party carried which risks.
“Main Roads and TS shared the risk on bridge foundations, a traditionally difficult area, as we decided cost savings could be achieved by taking on the risk jointly. This risk provision was taken out of the contingency, which kept the price down, and when the risk did not eventuate there was a win-win for both parties,” he said.
To be continued next month.
| Tweet |
Weekly Top Stories
- Plan approved for Melbourne Airport upgrade
- Walking and cycling projects receive green light
- Hansen Yuncken completes second Costco store
- Aussie Mine Boss
- Ritchie Bros. sets auction records
- Leighton Contractors awarded M5 East contract
- Powerscreen app makes info accessible
- Moreton Bay Rail Link reaches first milestone
- Fielder Instrument joins Position Partners
- Isuzu at the top of their game
- CSQ Excellence Awards honour industry’s best
- Hansen Yuncken awarded Cairns Terminal contract
- IntelliTrac launches GPS fleet tracking and fleet card
- Untreated sewage flows into Darwin harbor
- KOMTRAX recovers stolen machine
- Movers and Shakers
- Better flow for new Bobcat
- IPAF launches incident database
- Liebherr crane a tight yet perfect fit
- Liebherr crane a tight yet perfect fit
- Construction industry caught in slow lane
- Anzac Bridge announced as people’s choice
- Victoria to receive second container port
- High efficiency aircon system takes prize
- Leica Geosystems offer webcast for customers
- SkillsTech Australia encourages manufacturers to target apprentices
- Ritchie Bros Geelong is expanding
- San Francisco-Oakland Bay Bridge : A mega project
- Chinese workers concern WorkSafe & CFMEU
- Terex showcases successful recruitment program
- Top 3 overlooked ways to maximize scan data
- Construction leaders are big winners in the 2011 Australian Business Awards
- Hillhead Show proves popular with exhibitors
- Onsite Rental Group launches in Geelong
- AIMEX 2011 ‘theme day’ details announced
- Standards bring order to a volatile world
- De-watering pump primed for big projects
- Daring design to honour Australian icon
- One of engineering’s finest recognised
- Welcome upgrades to Hobart Airport
- Thiess Barnard JV to build new Queensland dam
- Fines levied after man falls 14 metres
- Tadano launches aussie-spec 60t truck crane
- John Holland secures Robertson Barracks
- Vandals strike on earthmoving equipment
- New Sandvik website improves information access
- Job creation fund to stimulate regional business
- Melbourne Park installs new water management
- Clean technology competition drives ingenuity
- Comfort and power are priorities for Takeuchi
- 2011 SkillsDMC Regional Roadshow
- CIVENEX: more relevant than ever
- Hillhead 2012 filling up quickly
- Historic South Brisbane Station on track for upgrade
- Portable MIG welder shows intelligence
- Sitemaster offers greater traction and durability
- Sydney International Airport car park awarded
- Queensland leads way with Clean Air technology
- Australia’s largest wind farm - NSW Project of the Year
- Shell Diesel Extra delivers new benefits
- New light vehicle training facility opens
- Severe skills shortages to be expected across all engineering professions
- 2011 Tasmanian Earth Awards – The Winners
- NSW RTA to host international bridge conference
- Coming to grips with safety on the road
- Volvo honours Europe’s top operator
- Apprentice forklift tech wins trip to USA
- Ritchie Bros conducts final 2011 auction and sets new records
- The king of rock
- Wastewater scheme picks up prestigious award
- $558 million fund to deliver real reform and skills for 130,000 Australians
- WA to enjoy fruits of labour
- School students try a trade
- Cyclone shelters out to tender
- Construction remains strong in the ACT
- JCB announces $47m new engine development
- Kennards launches new hire divisions
- Queensland’s reconstruction surges past $3bn mark
- Abigroup completes Perth bridge overpass
- Custom Fluidpower makes access easy
- $6bn Barangaroo development gets under way
- Deister celebrates a century of excellence
- All wheel steer for new Bobcat
- Abigroup secures new projects
- 50t payload for construction hovercraft
- Intract opens doors for Indigenous Australians
- Perth City Link vision takes shape
- Tier 4 engines set contractors apart
- Desal Discovery Centre to open this week
- Sydney Opera House receives new pipes
- Baulderstone JV tackles southern duplication
- Kiwi company Surveylab signs deal
- Installation underway on $26.9m Woolner substation
- Union penalised $26k for official’s behaviour
- John Holland to deliver Opera House project
- Online training to increase safety
- Runway projects up for grabs
- New $60m Melbourne Water main completed
- New guide eases family pressures of working away
- SAF Threadbar launches in Australia
- Strong growth continues for Viewpoint
- Manitou launches two new websites
- UQ funds engineers of tomorrow
- Woman’s guide to thriving in mining
- Construction industry confidence down
- Powerful mobile computer toughens up
- Consultation begins for environment law cost recovery
- MCG’s Great Southern Stand to receive major upgrade
- Manitou and Yanmar announce alliance
- Ready ... set ... mix !
- State supports Carnarvon flood mitigation
- Komatsu offers entry level pairing
- Leica Geosystems announces Hexagon 2012
- Free information sessions on new WH&S laws
- Hansen Yuncken tackles Townsville Uni
- TMHA lifting spirits at Mission Australia
- Case F-Series boosts economy and performance
- UQ scoops national chemical engineering awards
- New VHF safety network launched
- Position Partners joins Pointools sales partner program in Australia
- SA blows competitors away
- New Holland website goes mobile
- Reduce costs with Business Center – HCE
- EPG Engines launches PowerForce generators

Previous:
CFMEU organiser’s assaults “extreme…unacceptable”

